Torrent Power, Ahmedabad: net-meter, step by step.

नेट-मीटर कैसे लगवाएँ, स्टेप बाय स्टेप

Generic PM Surya Ghar flow. Net-meter charges for a single-phase home with 1 to 6 kW of solar: ₹5,408.64 payable, from Torrent's own charge sheet. Local office details and typical days are still to be confirmed.

  1. 1Registered · रजिस्टर करें
  2. 2Feasibility · फ़िज़िबिलिटी
  3. 3Vendor selected · वेंडर चुनें
  4. 4Agreement · एग्रीमेंट
  5. 5Installation · इंस्टॉलेशन
  6. 6Net-meter request · नेट-मीटर रिक्वेस्ट
  7. 7Inspection · इंस्पेक्शन
  8. 8Commissioning · कमीशनिंग
  9. 9Subsidy · सब्सिडी
Before you apply

Documents, fees and time.

Page data as of 2026-09-29. Anything we have not verified for Torrent Power, Ahmedabad is marked.

Documents

  • Latest electricity bill (consumer number)verify
  • Identity proof of the connection holderverify
  • Bank account details of the connection holderverify
  • Photos of the installed systemverify
  • DCR certificate for the panelsverify

Fees and time

Fees: ₹5,408.64. For a PM Surya Ghar home on a single-phase connection with single-phase solar of 1 to 6 kW: smart meter ₹4,459.70 + solar generation meter box ₹1,573.89 + GST ₹825.05 + connectivity ₹1,500 = ₹8,358.64, less a "Govt. Subsidy" line of ₹2,950 = ₹5,408.64 payable. On a three-phase connection up to 15 kW with three-phase solar of 1 to 6 kW: ₹11,597.50, or ₹8,647.50 payable. Source: Torrent Power "Solar Net-Metering Charges for MNRE Scheme (Ahmedabad)", one page with no printed date (PDF created 23-07-2026), linked on Torrent's solar guide as the National Portal scheme sheet; read 29-09-2026. Torrent also posts an "Additional" national-portal table (₹8,619.64 single-phase) without saying when it applies, so ask which one your quotation uses.

Typical days: to verify. To verify from DISCOM data or installer reports.

Tariff on file: FY 2026-27, verified.

Official portal (National portal. DISCOM's own rooftop page to verify.)

  1. 1Registered · रजिस्टर करेंRegister on the PM Surya Ghar national portal with the consumer number from the electricity bill.
  2. 2Feasibility · फ़िज़िबिलिटीThe DISCOM checks the connection and sanctioned load and approves feasibility.
  3. 3Vendor selected · वेंडर चुनेंThe consumer picks an empanelled vendor on the portal.
  4. 4Agreement · एग्रीमेंटThe consumer approves the agreement with the vendor on the portal.
  5. 5Installation · इंस्टॉलेशनThe vendor installs the system and uploads photos and details.
  6. 6Net-meter request · नेट-मीटर रिक्वेस्टA net-meter is requested from the DISCOM after installation.
  7. 7Inspection · इंस्पेक्शनThe DISCOM inspects the installation and the meter.
  8. 8Commissioning · कमीशनिंगThe DISCOM issues the commissioning certificate on the portal.
  9. 9Subsidy · सब्सिडीThe central subsidy is credited to the consumer's bank account.

On the blog

The full write-up on the Torrent Ahmedabad net-meter process: Torrent Power net-meter process, step by step