Documents, fees and time.
Page data as of 2026-09-29. Anything we have not verified for MP Madhya Kshetra Vidyut Vitaran Co. (MPMKVVCL) is marked.
Documents
- Latest electricity bill (consumer number)verify
- Identity proof of the connection holderverify
- Bank account details of the connection holderverify
- Photos of the installed systemverify
- DCR certificate for the panelsverify
Fees and time
Fees: No processing fee and no meter-testing fee for PM Surya Ghar applications. MPERC (Grid Interactive Renewable Energy Systems Related Matters) Regulations [Revision-II] 2024 (First Amendment), ARG-39(II)(i) of 2026, No.1016/MPERC/2026 dated 18-06-2026, cl.3.1: "prosumers applying for net metering connections under PM Surya Ghar Muft Bijli Yojna (PMSG:MBY) shall not be required to pay aforesaid processing fee"; cl.3.3: "the Licensee shall not charge any fee for testing of meters" for these connections. Outside PM Surya Ghar the processing fee is ₹1,000 (RG-39(II) of 2024, Reg 6(d)). The bi-directional meter is "at the cost of the prosumer" (RG-39(II) Reg 10(3)); its price was not found, so no total is shown. Read 29-09-2026.
Typical days: to verify. To verify from DISCOM data or installer reports.
Tariff on file: FY 2026-27, verified.
Official portal (National portal. DISCOM's own rooftop page to verify.)
- 1Registered · रजिस्टर करेंRegister on the PM Surya Ghar national portal with the consumer number from the electricity bill.
- 2Feasibility · फ़िज़िबिलिटीThe DISCOM checks the connection and sanctioned load and approves feasibility.
- 3Vendor selected · वेंडर चुनेंThe consumer picks an empanelled vendor on the portal.
- 4Agreement · एग्रीमेंटThe consumer approves the agreement with the vendor on the portal.
- 5Installation · इंस्टॉलेशनThe vendor installs the system and uploads photos and details.
- 6Net-meter request · नेट-मीटर रिक्वेस्टA net-meter is requested from the DISCOM after installation.
- 7Inspection · इंस्पेक्शनThe DISCOM inspects the installation and the meter.
- 8Commissioning · कमीशनिंगThe DISCOM issues the commissioning certificate on the portal.
- 9Subsidy · सब्सिडीThe central subsidy is credited to the consumer's bank account.
On the blog
The full write-up on the MPMKVVCL net-meter process: MP rooftop solar net-meter process: East, Central and West DISCOMs
Track every net-meter request.
Raymitra shows each application's stage and days pending, per DISCOM.
- +91 88154 11655